November 2019

November 2019

Preparatory works have already been completed, i.e. fencing the construction site, preliminary surveying service – setting out the building by a surveyor, terrain grading, connecting technical infrastructure for the needs of the construction and also the organization of the construction site infrastructure.

 

At present, earthworks are being performed connected with the construction of underground stories to locate the garage, the indoor swimming pool complex, the bowling alley, the technical facilities and the conference section of the hotel. 70% of perimeter walls of underground stories has been completed in the cavity wall system. The walls are built by the French company Soletanche Polska Sp. z o.o., with its registered office in Warsaw, while earthworks involving the excavation works for the underground garage and the groundslab placed over 12 meters below ground level were taken up by Silvernix Sp. z o.o. from Warsaw as a general contractor. The entity responsible for the architectural design of the investment project is the renowned studio Piotr Płaskowicki & Partnerzy Architekci – the winner of Property Design Awards 2018 in the category Building Exterior – Hotel.

 

Strona używa cookies (ciasteczek). W przeglądarkach internetowych można zmienić ustawienia dotyczące cookies. Zablokowanie możliwości zapisywania plików cookies może spowodować utrudnienia lub brak działania niektórych funkcji serwisu. Niedokonanie zmian ustawień przeglądarki internetowej na ustawienia blokujące zapisywanie plików cookies jest jednoznaczne z wyrażeniem zgody na ich zapisywanie.Zamknij